Master Suite Renovation- Project Update 2
Just two weeks ago we posted progress photos of this project.
Due to the pool below, all of the mechanicals had to be roughed-in from the top down. Under normal circumstances, the subfloor usually remains in place and the mechanicals are installed through the underside.
Normally interior wall framing is built on top of the subfloor. In this situation, the subfloor had to remain uninstalled until all the mechanicals and foam insulation was installed. The interior walls were framed and installed using a build-up of material so that the door ways would be flush after the subfloor was installed.
Watch a video of this project getting spray foam insulated here and learn more about it in an upcoming post.
We started this project August 6th. As of today (August 31), we have started ceiling and wall painting.